Status: In Progress
Project Number: 19
Category: Multi-Use Path System
Location: North Peachtree Pkwy
Proposed Project Year: 2021
Original Project Budget: $300,000
Project/Goal Description: New path along Peachtree Parkway from Walt Banks to Lake Kedron Crossing.
December 2022 Progress Update: Public Works contracted out surveying of the right-of-way, property lines, and topography for this corridor, and this has been completed. Public works have started the design of this path extension to include grading and drainage. Easements will be needed in certain areas to accommodate path construction.
SPLOST Actuals Total: $10,500
SPLOST Funds Remaining: $289,500
Proposed Project Photo:

Final Project Photos: N/A