Current Development
As of September 8, 2023
RESIDENTIAL PROJECTS
Project Name/ Address (Click for map of location) | Initial Plat | Construction Drawings | Site Development & Building Construction | Final Plat |
---|---|---|---|---|
Cresswind single-family MacDuff Parkway | Approved 2015 | Approved 2017-2021 | 748 total lots 95% complete | Approved 2016-2022 |
Everton single-family MacDuff Parkway | Approved 2016 | Approved 2016-2020 | 788 lots 74% complete | Approved 2016-2022 |
Laurel Brooke Mixed-Use single-family phase Petrol Point | Approved 2019 | Approved 2021 | 16 lots 20% complete | Approved 2021 |
Laurel Brooke Mixed-Use townhome phase Petrol Point | Approved 2019 | Approved 2021 | 6 lots In Progress | Approved 2021 |
MacDuff Parkway Townhomes townhomes MacDuff Parkway (near railroad) | Approved July 2023 | 30 Townhomes | ||
Mill Farms single-family Redwine Road | Approved 2021 | Approved Jan. 2022 Amendment in progress | 74 lots Site work in progress | |
Rockaway Townhomes townhomes Rockaway Rd | Approved 2020 | Approved May 2022 | 30 townhomes In Progress | |
Smokerise Corners single-family Sumner Road | Approved 2019 | Approved 2020 | 26 lots 50% complete | Approved 2022 |
Towson Village Mixed Use single-family phase Governors Square | Approved 2020 | Approved 2021 | 94 lots In Progress | Phase 1 Approved Feb. 2023 |
Wilksmoor Woods single-family MacDuff Parkway | Approved 2018 | Approved 2019 | 180 lots 91% complete | Approved 2020-2022 |
COMMERCIAL PROJECTS
Project Name/ Address (Click for map of location) | Conceptual Site Plan | Construction Drawings | Site Development | Building Construction |
---|---|---|---|---|
Aberdeen Mixed-Use 12 condos & ground commercial 215 Northlake Drive | Approved Nov. 2022 | In Progress | Building elevations approved Dec. 2022 | |
Aventure Aviation warehouse expansion 108 International Drive | Approved 2021 | Approved Feb. 2023 | ||
Bradshaw Corners office/ commercial lots 54 East near Sumner Rd | Approved 2019 | In Progress | ||
Bridge Park Medical medical office/ pharmacy 2035 N Commerce Dr | Approved March 2023 | In Progress | Building elevations approved July 2023 | |
CertainTEED Expansion manufacturing expansion 200 Sierra Dr | Approved 2017 | Approved June 2023 Amendment in Progress | In Progress | |
Gerber Collision automotive 445 HWY 74 S | Approved 2022 | Approved Feb. 2023 | In Progress | Building plans approved July 2023 |
Gerresheimer Expansion manufacturing expansion 650 HWY 74 S | Approved Sept. 2022 | Approved March 2023 | In Progress | Building plans approved May 2023; In progress |
Gerresheimer New Site manufacturing 305 Naeco Way | Approved July 2023 | |||
Gimme Shelter Expansion public storage facility 1150 HWY 74 S | Approved March 2023 | |||
Hoshizaki Expansion manufacturing expansion 618 HWY 74 S | Approved Aug. 2023 | |||
Integrity Fusion 2nd Building manufacturing warehouse 270 Parkade Court | Approved July 2023 | |||
Laurel Brooke Mixed-Use condominium building 2 1050 Blair Ln | Approved 2019 | Approved 2021 | ||
Laurel Brooke Mixed-Use amenity building 4000 Hayes Sq | Approved 2019 | Approved 2021 | Complete | Complete |
Meditec Manufacturing manufacturing 782 S HWY 74 | Approved April 2023 | In Progress | Building elevations approved Aug. 2023 with conditions | |
Peachtree Cardiology medical office 100 McWilliams Drive | Approved Feb. 2023 | Approved July 2023 | In Progress | Building elevations approved May 2023 |
Residence Inn extended stay hotel 400 World Drive | Approved 2020 | Approved Feb. 2023 | In Progress | Building plans approved July 2023 |
Self Storage (New) self storage 425 HWY 74 S | Approved July 2023 | |||
Sherwin-Williams paint store 1110 Crosstown Court | Approved June 2023 | Not required | In Progress | Building elevations approved Aug. 2023 |
Silon Expansion manufacturing expansion 101 Sierra Drive | Approved Aug. 2022 | In Progress | ||
Starr's Mill Medical medical office 110 Wilshire Village Dr | Approved Sept. 2022 | Approved May 2023 | Building elevations approved Sept. 2022 | |
SWI Machinery Inc manufacturing 400 Naeco Way | Approved May 2023 | |||
Take 5 Oil Change automotive 2714 HWY 54 W | Approved Feb. 2023 | In Progress | Building elevations approved July 2023 | |
The Gates Medical medical office 101 Gates Entry | Approved Dec. 2022 | Approved May 2023 | Building elevations approved July 2023 | |